Baru Gold Corp. (BARU: TSX.V | BARUF: OTCQB) (“Baru”) and its subsidiary PT. Tambang Mas Sangihe (“TMS” or the “Company”) are pleased to report progress in advancing its production readiness at the Sangihe Gold Project while awaiting approval for the upgrade to production operations.
The Company has successfully concluded a competitive bid and tender for the design and construction of an Electrowinning Elution Column Plant.
An Electrowinning Elution Column Plant is a modern gold recovery facility that automates the extraction of gold from leach solutions. Gold adsorbed onto resin is first separated in an elution column to produce a concentrated gold-bearing solution, which then passes through electrowinning cells where an electrical current deposits pure metallic gold onto cathodes. The process is fully automated, highly efficient, environmentally friendly, and delivers excellent recovery rates.
A leading Indonesian engineering and construction company was awarded the contract to design and assemble the plant, which will be manufactured locally in Indonesia. Producing the plant domestically supports the local economy while reducing costs and delivery times. The electrowinning system is inexpensive costing only a few hundred thousand dollars and can become fully operational within several months.
This strategic decision was led by Baru’s Chief Operating Officer, Sri Darmawan, who brings over 30 years of experience working with some of the largest gold mining companies in North Sulawesi. His extensive knowledge of regional conditions, proven technologies for similar ore bodies, and understanding of local contractor capabilities was instrumental in selecting a cost-effective, high-quality solution.
Mr. Terrence Filbert, CEO of Baru Gold, commented, “We are making excellent progress as we prepare for the transition to production operations. While awaiting the remaining approvals for Production Operations, we are effectively using this time to lay the groundwork for rapid implementation. I am preparing for operational readiness while conserving capital, ensuring that once the necessary approvals are granted, the Company can commence gold production without delay.
Key Highlights of the Production Plant Design